Working example 04 Monte Carlo and value of information

Decisions with incomplete evidence

“We must make a major decision before we have all the information.”

A logistics business must decide whether to build a £12m distribution centre. Demand is uncertain, construction costs can overrun and the ramp-up could take one to three years. A market study is on offer.

The business context

The problem and the solution

The business problem

A logistics business must decide whether to build a distribution centre before it knows the demand, final building cost or time needed to reach full use. A single forecast hides the risk of a poor investment.

How the solution helps

The solution works through 20,000 possible futures and calculates whether the centre pays back in each one, allowing for the time value of money. It shows the average result, the chance of losing money and which unknowns matter most. It also estimates the most that perfect knowledge of demand could be worth. A real study leaves uncertainty, so this is a ceiling on its value, not proof that a study will pay for itself.

Explore the evidence

The input dataset

This example uses assumptions and generated scenarios, not historical records. Each scenario is one possible future used to calculate investment value. Sliders update demand and building cost while reusing the same underlying random draws for a fair comparison. Calculated investment returns are outputs and are excluded from these input tables.

All records are illustrative and generated in your browser. Browse every row using the table controls. Displayed decimals are rounded; calculations use full precision.

How it works

The method in three steps

  1. Describe uncertaintyDemand is normally distributed around the estimate, margin is triangular (£18–£28 per pallet), build cost is log-normal and ramp-up is one, two or three years.D ~ N(μ, σ), m ~ Tri(18, 24, 28), C ~ 12·LogN(0, s)
  2. Simulate valueEach draw produces a 10-year net present value at 8%, with capacity capped at 160,000 pallets a year.NPV = −C + Σ (min(D_t, cap)·m − opex) / 1.08ᵗ
  3. Price the informationExpected value of perfect information (EVPI) bounds what any research is worth; partial EVPI isolates each uncertainty.EVPI = E[max(NPV, 0)] − max(E[NPV], 0)

Try it

The working example

Assumptions

Change what you believe and see whether the decision changes.

Thousand pallets a year at full ramp-up
One standard deviation
Log-normal spread of capital cost
Would resolve demand uncertainty
Expected NPV–
Chance of losing money–Share of simulations with NPV below zero
Value of perfect information–The most any research could be worth
Recommendation–

Range of outcomes

20,000 simulated 10-year NPVs. Orange outcomes lose money.

Which uncertainty is worth resolving?

Expected value of perfect information for each uncertainty, against the cost of a demand study.

Interpretation

From example to engagement

What the example shows

A single-point business case hides the chance of loss and the shape of the downside. Value-of-information analysis turns “we need more data” into a priced question: some uncertainties matter to the decision and are worth paying to reduce, and others are not, however large they look.

With real data

  • Distributions elicited from experts and calibrated against history.
  • Correlations between inputs, such as demand and price.
  • Expected value of sample information (EVSI) for studies that reduce rather than remove uncertainty, and real options for staged investment.